This paper proposes a real-time solution to the unit commitment problem by considering different constraints like ramp-up rate, unit operation emissions, next hours load, and minimum down time. In this method, an optimized trade-off between cost and emission has been taken into consideration. The effectiveness of the proposed method was verified by the significant outcomes demonstrated.

DOI

10.3906/elk-1105-42

Keywords

Unit commitment, artificial neural network, genetic algorithm

First Page

198

Last Page

212